Primary Intelligence Asset
ELECTRIFYING MONTHS AT CHINESE DOMESTIC AGENCY AND ITER’S ELECTRICAL ENGINEERING DIVISION
Declassified Public record OCR verified
INTEL
Executive Summary
This document outlines major milestones achieved by the Chinese Domestic Agency (CN-DA) and ITER's Electrical Engineering Division between April and July 2012. Key accomplishments include finalizing Procurement Arrangements (PAs) and conducting Preliminary Design Reviews (PDRs) for critical power systems including the Pulsed Power Electrical Network (PPEN), Poloidal Field AC/DC Power Converters, and Reactive Power Compensation and Harmonic Filtering (RPC&HF) System, collectively representing over 35% of China's in-kind contribution to ITER.
Analysis Confidence: High
ST_CODE: HINAOK
System Metadata
Source ID
DOC-CHINA_OK
Process Date
Public archive record
Integrity Hash
SHA256-CHINAOK...
Indexer Status
COMPLETE
Initializing_Secure_Viewer...
Full Transcript
Transcript
Page 1 of 3
Page 1
ELECTRIFYING MONTHS AT CHINESE DOMESTIC AGENCY
AND ITER’S ELECTRICAL ENGINEERING DIVISION
By Ling Dong, ITER China & Ivone Benfatto, ITER Organization
Finalizing the signature of a Procurement Arrangement(PA)and, at the same time, organizing Preliminary Design Reviews (PDR) for two major systems is a very demanding task that the Chinese Domestic Agency (CN-DA) and ITER’s Electrical Engineering Division performed between April and July 2012.
Assembly of documentation for the materials of the PA for the Pulsed Power Electrical Network (PPEN) worth 21.9 kIUA, was finalized between January and June 2012 and signed at the last ITER Council in Washington, D.C.
During the same period, the Preliminary Design Reviews for two other major power supply PAs had to be organized; these took place last week in Beijing for both the Poloidal Field AC/DC Power Converters (worth 61.1 kIUA) and for the Reactive Power Compensators and Harmonic Filtering System (worth 16.5 kIUA).
Together these three PAs exceed 35% of the CN-DA’s total in-kind contribution to ITER.
Participants to the meetings
Frequently Asked Questions
What is this document? ▾
This document outlines major milestones achieved by the Chinese Domestic Agency (CN-DA) and ITER's Electrical Engineering Division between April and July 2012. Key accomplishments include finalizing Procurement Arrangements (PAs) and conducting Preliminary Design Reviews (PDRs) for critical power sy...